Jump to the beginning of content

Water Supplies Department - Annual Report 2012/13 Living the Legacy; Exploring New Frontiers

Meeting the Demand for Water

Hong Kong enjoys the benefits of a water supply that boasts greater reliability as a result of improved infrastructure and increased monitoring of distribution networks.
IMPROVING THE SUPPLY NETWORK
Annually, the number of reported cases of burst water mains has reduced from 2 500 in 2000/01 to just 267 in 2012/13. Our 15-year phased programme of replacing and rehabilitating 3 000 km of water mains has resulted in greater supply reliability. Hong Kong has over 8 000 km of water mains, many of which are more than 30 years old. The current replacement and rehabilitation programme has focused on 3 000 km. The programme has reached its final stage and, as at 30 April 2013, we had completed work on 2 091 km of water mains, reducing water mains bursts, sudden drops in pressure and other incidents that can disrupt water supplies and, in many cases, cause traffic and transport disruptions. The current replacement and rehabilitation programme will be completed by 2015 and plans are in hand to launch a second phases of replacement and rehabilitation involving some of the remaining 5 000 km of mains.
Pipe rehabilitation work of large diameter pipe photo
Pipe replacement work photo
Pipe rehabilitation work – spray applied lining photo
Statistics on Leak Detection
Fresh Water
Tests Conducted Per Financial Year
2008/09 2009/10 2010/11 2011/12 2012/13
No. of Minimum Night Flow Tests 278 276 241 174 139
No. of Step Tests (or Leakage Tests) 65 30 27 25 13
No. of Sounding & Visual Inspections 4 438 4 914 3 177 3 221 3 282
No. of Leaks Detected 2 598 2 563 1 846 2 006 1 432
Estimated Quantity of Fresh Water Saved (cubic metres/day) 127 244 93 731 75 299 79 531 57 128
Sea Water
Tests Conducted Per Financial Year
2008/09 2009/10 2010/11 2011/12 2012/13
No. of Minimum Night Flow Tests 0 0 0 0 0
No. of Step Tests (or Leakage Tests) 2 2 0 0 0
No. of Sounding & Visual Inspections 207 155 304 532 516
No. of Leaks Detected 153 154 124 154 127
Estimated Quantity of Sea Water Saved
(cubic metres/day)
113 201 18 204 29 918 21 719 35 040
The programme involves advanced construction methods and technologies. Where necessary, we have used trenchless construction methods including close fit lining of existing mains, cure in-place pipes, pipe jacking and horizontal directional drilling to reduce on the ground construction and lessen inconvenience for the public.

In addition to the urban work currently being undertaken, we will replace a submarine pipeline from Lantau Island to Cheung Chau. A horizontal directional drilling method will be used to lay the new submarine pipeline to minimise the impact of the work on the environment, nearby marine and terrestrial archaeological sites and marine traffic. This project is scheduled to commence in September 2013 and should be completed by September 2015.

Shek Pik Reservoir in Lantau Photo
Siu Ho Wan Water Treatment
Works in Lantau Photo
MAXIMISING INFRASTRUCTURE
We are constantly looking at ways to generate more water from our existing resources and catchments. In conjunction with Drainage Services Department's flood control strategy for West Kowloon, we are planning an Inter-reservoirs Transfer Scheme which will connect the Kowloon Group of reservoirs with Lower Shing Mun Reservoir using a raw water transfer tunnel. Flood water, instead of being discharged into Victoria Harbour, will be carried through a tunnel and along an existing transfer system to the Sha Tin Water Treatment Works where it will be treated for supply. The project is expected to generate an additional 2.5 million cubic metres to the local yield annually.
Improvements will be made to catchwaters to further ensure the safe and efficient collection of surface water. The first of these projects will involve improvements to 26 kilometres of catchwaters in the Shing Mun, Beacon Hill, Golden Hill and Tai Lam Chung catchwater systems.
IMPROVING SUPPLIES

We are constantly expanding and improving the infrastructure needed to ensure Hong Kong has adequate supplies of both fresh water and seawater. New initiatives include improvements to salt water systems and pumping stations at Chai Wan and Siu San Wan. An additional 4.6 km of salt water mains are being laid to meet the growing demand in the area. A salt water supply system to be used for toilet flushing in Tung Chung has proceeded to detailed design stage. Fresh water supplies to areas of Central are being improved through the expansion of the existing Albany Reservoir in Mid-Levels.

New housing development areas at Lok Ma Chau and Kwu Tung North will be catered for by construction of a new fresh water reservoir at Kwu Tung North.

The installation of a cross-harbour fresh water submarine pipeline, 1 200 mm in diameter and 2.1 kilometres in length, under the western part of Victoria Harbour between West Kowloon and Sai Ying Pun, has been completed. The new cross-harbour main not only helps to cater for the increased water demand of Hong Kong Island, but also plays an important role in enhancing the reliability of the fresh water supply to Hong Kong Island.
Capital Investment Photo Statistics on Mains Bursts Repaired Photo
Replacement of delivery mains under
reprovisioning of Sha Tin Water Treatment Works Photo


 
UPGRADING TREATMENT CAPACITIES

Planning and construction work is underway at the Sha Tin Water Treatment Works and the Tai Po Water Treatment Works respectively – two major facilities used to treat raw water before it is distributed across Hong Kong. The Sha Tin plant is to be reprovisioned while the Tai Po plant is undergoing a significant expansion. Both will ensure that we have adequate capacity to treat raw water to current drinking water standards and to higher standards should they be introduced in the future. Careful phasing of work means that at all stages of construction, the treatment capacities of the two facilities will meet the required aggregate demand for water.

The capacity of the Tai Po Water Treatment Works will be increased from 250 000 cubic metres per day to 800 000 cubic metres per day in two parts at a cost of $5.6 billion. Part 1, taking the treatment capacity up to 400 000 cubic metres per day, was completed in 2011. Part 2 of the Tai Po Water Treatment Works expansion which began in February 2013 will increase the capacity of the works to 800 000 cubic metres per day. The plant is due to be commissioned in 2017. The detailed design of the in-situ reprovisioning of the south works of the Sha Tin plant is underway and is scheduled for commissioning by the 2020s.

Other major improvement works undertaken include the retrofitting of the North Works of the Sha Tin water Treatment Works. Inclined tubes have been installed to improve the plants' treatment capacities. A clarifier at the Sheung Shui Water Treatment Works has also been retrofitted with inclined tubes to produce a similarly positive outcome.

Fresh water augmentation has been introduced at the salt water supply systems in Tsuen Wan and Kwai Tsing to enhance the reliability of flushing water supplies. We have also provisioned the decking over the Ha Lo Wai salt water reservoir for safety reasons.

Inclined tubes at clarifier of Sheung Shui Water Treatment Works Photo
OPERATIONAL EFFICIENCIES
We have upgraded our SCADA system which is used to centrally oversee facilities such as pumping stations and service reservoirs from four regional control centres to improve the operational efficiency of territory-wide water supply networks. To further enhance reliability of the system, alternative control centres are being established at each of our four operational regions in Hong Kong. The alternative control centre for the New Territories West region is already operating whilst the remaining three new centres are under construction.
Control systems at water treatment works at Yau Kam Tau, Ma On Shan, Pak Kong, Sheung Shui and Tsuen Wan have been upgraded and similar upgrade programmes are underway at Ngau Tam Mei and Tuen Mun water treatment works and some key pumping stations to ensure efficient, reliable and effective operations. Across the board, IT infrastructure and application systems have been introduced to enhance the quality of services.
In line with on-condition monitoring studies, we are continuing to improve the performance of plant equipment. A web-based management system to monitor pumping efficiency has been successfully tested for rolling out at 10 pumping stations. To facilitate maintenance without causing supply interruption, we are adding compartment walls to sea water service reservoirs which currently operate with just single compartments.
When there is an emergency situation such as a mains burst, our first recourse is to maintain an uninterrupted supply by shifting the water supply zone wherever possible. If this is not possible, we will provide a temporary fresh water supply to customers to meet their basic need should they face a temporary suspension of supplies due to an emergency which is expected to last for more than three hours. Emergency temporary fresh water supplies are provided through standpipes, water wagons or water tanks. To enhance the service, we have doubled our fleet of water wagons to 10.
OPTIMISING ASSETS

We aim to manage the life cycle of all water services infrastructure so that we can achieve a desired level of service cost-effectively and within an acceptable risk framework.

Over the past year we have completed four surface assets management plans. These plans identify the performance and physical condition of some 900 waterworks installations. Once improvement works have been identified, they are prioritized for implementation over the coming years. Under a Reliability-Centred Maintenance programme we have completed the review at a water treatment plant and two key pumping stations. As a result, we have the basis for a comprehensive model of maintenance strategies for mechanical and electrical assets. The programme will be rolled out at another water treatment works and two more pumping stations in 2013 for continuous improvement of services.

Slope maintenance remains an important programme. The maintenance of almost 6 500 slopes has been assigned to the Department by the Lands Department. In turn, we routinely inspect these slopes and, where necessary introduce monitoring, maintenance and upgrading measures to reduce any deterioration in stability.
Water quality monitoring during field exercise for Daya Bay Contingency Plan Photo

CRISIS MANAGEMENT

We are constantly identifying and managing risks across the entire supply system. Crisis management and the ability to maintain an uninterrupted water supply should any extraordinary event occur are ongoing challenges. A crisis management plan and various contingency plans are in place to maintain a state of preparedness for the rapid mobilisation of resources and the co-ordination of emergency actions.

In April 2012, the Department participated in an inter-departmental exercise involving the Government's Daya Bay Contingency Plan. The exercise simulated an off-site incident at the Guangdong Nuclear Power Station. Both desktop and field exercises were successfully conducted to test the effectiveness of our Daya Bay Contingency Plan and to monitor the level of coordination achieved with other departments in handling an emergency at the power plant.