Project Scope
- increasing the water treatment capacity of the Ngau Tam Mei water treatment works (NTM WTW) from 230 000 cubic metres (m3) per day to 440 000 m3 per day by constructing new water treatment facilities within the existing NTM WTW and enhancing the existing associated facilities, and providing spare space in the new facilities to cater for possible further increasing of water treatment capacity up to 640 000 m3 per day to cater for the demands in future;
- laying approximately 8 kilometres (km) long of fresh water trunk mains with diameter ranging from 1 400 millimetres (mm) to 2 000 mm from the NTM WTW to the fresh water supply systems near Pok Oi Interchange and Tan Kwai Tsuen;
- constructing an approximately 0.6 km long tunnel for the laying of raw water mains with diameter ranging from 2 000 mm to 2 800 mm with provision of vehicular access, two raw water main connection chambers (namely “Chamber G2” and “Chamber G3”) for connections with the existing raw water tunnels and a ventilation building and a tunnel portal within the WTW, and providing ventilation and fire fighting systems inside the tunnel for the purpose of daily operation and maintenance;
- extending Ngau Tam Mei fresh water primary service reservoir for an additional capacity of about 54 000 m3; and
- carrying out other associated works.
Approved Project Estimate
$9,608.5 million
Construction Commencement Date
October 2025
Estimated Construction Completion Date
Second quarter of 2031
Current Progress
Construction is in progress
Project Office in WSD
Consultants Management Division
Consultant
Ove Arup and Partners Hong Kong Limited
Contract
- Contract No. 3/WSD/24 - Ngau Tam Mei Water Treatment Works Extension – Extension of Ngau Tam Mei Fresh Water Primary Service Reservoir, Modification of Raw Water Tunnel Junction (Chamber G) and Associated Mainlaying
(NEC HK Edition ECC Option C)
- Contract No. 18/WSD/24 - Extension of Ngau Tam Mei Water Treatment Works and Associated Improvement Works of Existing Treatment Stream
(NEC HK Edition ECC Option C)
Contractor
- Contract No. 3/WSD/24: Chun Wo – CCECC Joint Venture
- Contract No. 18/WSD/24: CRBC – CNCEC Joint Venture