9377WF
Improvement of water supply to northern New Territories
Project Scope
- laying of about 5.2 kilometres (km) long fresh water trunk mains of diameters ranging from 600 millimetres (mm) to 1 400mm from Tai Po Water Treatment Works to Fanling;
- construction of a new Fresh Water Pumping Station in Tong Hang with a pumping capacity of about 400 000 cubic metres (m3) per day;
- modification of the existing pumps and associated electrical and mechanical installations in the existing Tai Po FWPS; and
- carrying out other associated works.
Approved Project Estimate
$1,035.6 million
Construction Commencement Date
October 2025
Estimated Construction Completion Date
Fourth quarter of 2030
Current Progress
Construction is in progress
Project Office in WSD
Construction Division
Consultant
Asia Infrastructure Solutions Limited
Contract
Contract No. 6/WSD/25 – Improvement of Water Supply to Northern New Territories
(NEC HK Edition ECC Option C)
Contractor
MH-CY Joint Venture
9377WF