9377WF

Improvement of water supply to northern New Territories

Project Scope

  1. laying of about 5.2 kilometres (km) long fresh water trunk mains of diameters ranging from 600 millimetres (mm) to 1 400mm from Tai Po Water Treatment Works to Fanling;
  2. construction of a new Fresh Water Pumping Station in Tong Hang with a pumping capacity of about 400 000 cubic metres (m3) per day;
  3. modification of the existing pumps and associated electrical and mechanical installations in the existing Tai Po FWPS; and
  4. carrying out other associated works.

Approved Project Estimate

$1,035.6 million

Construction Commencement Date

October 2025

Estimated Construction Completion Date

Fourth quarter of 2030

Current Progress

Construction is in progress

Project Office in WSD

Construction Division

Consultant

Asia Infrastructure Solutions Limited

Contract

Contract No. 6/WSD/25 – Improvement of Water Supply to Northern New Territories 

(NEC HK Edition  ECC Option C)

Contractor

MH-CY Joint Venture