9369WF

Uprating of Sheung Wong Yi Au fresh water supply system - stage 1

Project Scope

  1. uprating of the existing Ha Wong Yi Au (HWYA) fresh water pumping station; and
  2. laying of associated fresh water mains with diameters ranging from 400 millimetres (mm) to 600 mm with an approximate total length of 5.5 kilometres (km).

Approved Project Estimate

$207.0 million

Construction Commencement Date

September 2020

Construction Completion Date

June 2025

Current Progress

Completed

Project Office in WSD

Construction Division

Consultant

Not applicable

Contract

Civil Contract

Mechanical & Electrical Contract