9369WF
Uprating of Sheung Wong Yi Au fresh water supply system - stage 1
Project Scope
- uprating of the existing Ha Wong Yi Au (HWYA) fresh water pumping station; and
- laying of associated fresh water mains with diameters ranging from 400 millimetres (mm) to 600 mm with an approximate total length of 5.5 kilometres (km).
Approved Project Estimate
$207.0 million
Construction Commencement Date
September 2020
Construction Completion Date
June 2025
Current Progress
Completed
Project Office in WSD
Construction Division
Consultant
Not applicable
Contract
Civil Contract
- Contract No. 2/WSD/19 - Mainlaying and Uprating of Ha Wong Yi Au Fresh Water Pumping Station
(NEC3 ECC Option B)
Mechanical & Electrical Contract
- Contract No. 14/WSD/19 - Uprating of Ha Wong Yi Au Fresh Water Pumping Station
(NEC3 ECC Option A)
9369WF