Project Scope
- construction of a service reservoir at Table Hill with a capacity of 24 000 cubic metres (m3);
- laying of two trunk mains of about 1 000 metres (m) in total, with a diameter of 600 millimetres (mm) connecting respectively the existing Sheung Shui water treatment works and Table Hill fresh water service reservoir with the new service reservoir; and
- laying of about 1 700 m distribution main of 800 mm in diameter connecting the new service reservoir with the existing fresh water distribution network at Tin Ping Road.
Approved Project Estimate
521.3M
Commencement Date
September 2016
Completion Date
April 2020
Current Progress
Substantial Completion.
Project Office in WSD
Construction Division
Consultant
NA
Contract
- 4/WSD/16 - Improvement of Water Supply to Sheung Shui and Fanling
(NEC3 ECC Option D)