Water Supply to Pak Shek Kok Reclamation Area, Tai Po – Stage 2
Project Scope
Laying of about 2.1 kilometres of fresh water mains of 600 millimetres in diameter between Pun Chun Yuen and Shan Tong New Village in Tai Po.
Approved Project Estimate
$162.7 million
Construction Commencement Date
December 2013
Construction Completion Date
March 2017
Current Progress
Completed
Project Office in WSD
Construction Division
Consultant
Not applicable
Contract
Contract No. 9/WSD/13 - Water Supply to Pak Shek Kok reclamation area, Tai Po – stage 2 phase 2
Contractor
Kwan On - U-Tech Joint Venture