Project Scope

  1. the uprating of Sha Tin seafront salt water pumping station (SWPS) to a total capacity of 112 000 m3 per day (m3 /day) by constructing an annex salt water pumping station of capacity of 17 000 m3 /day, and uprating of the existing facilities in Sha Tin seafront SWPS including valves and surge suppression equipment;
  2. the increase of pumping head of Sha Tin salt water booster pumping station by replacing the existing pumps with high-head pumps;
  3. the reconstruction of the existing To Shek salt water service reservoir (SWSR) for a storage capacity of about 8 800 m3 ;
  4. the construction of Ma On Shan No. 3 salt water service reservoir of storage capacity of about 1 200 m3 ; and
  5. the laying of about 3.5 kilometres (km) and rehabilitation of about 2.9 km of salt water mains of diameters ranging from 200 millimetres (mm) to 800 mm.

Approved Project Estimate

$207.4M

Commencement Date

29 February 2008

Completion Date

20 August 2012

Current Progress

100% completed

Project Office in WSD

Construction Division

Consultant

N/A