Project Scope

The works mainly comprise construction of Grey Water Treatment Plant for Anderson Road Quarry Site Development.

1. Construction of a grey water treatment plant in the development of Anderson Road Quarry Site with a production capacity of up to 3 300 cubic metres (m3) per day.

Sum Earmarked in Approved Project Estimates for the Contract

$484.3 million

Construction Commencement Date

September 2020

Construction Completion Date

December 2025

Current Progress

Completed

Project Office in WSD

Consultants Management Division

Consultant

Binnies Hong Kong limited

Contract

Contract No. 4/WSD/19 - Development of Anderson Road Quarry Site - Construction of Grey Water Treatment Plant

(NEC3 ECC Option C)

Contractor

Paul Y. - Tsun Yip Joint Venture