Before applying formally for water
supply, please check the lease condition of the development
to confirm whether mains water supply would be available.
You can write to the Water Authority and indicate briefly
your requirements with the exact location of the development
marked on a block plan.
If provision of water supply is feasible,
details of the requirements will be sent to you for
preparation of plumbing proposals. The plumbing proposals
should be sent together with completed application Form
WWO
542 to the Water Authority.
Plumbing works must NOT commence until
the plumbing proposals have been approved by this Office
in writing. Your licensed plumber is required to submit
Form WWO
46 to the Water Authority for confirmation of the
compliance of the pipes and fittings to be installed.
These proposals will then be studied, and should it
be necessary you will be asked to have them modified.
You should employ a licensed
plumber to install all pipework and fittings for
the supply of mains water.
When the plumbing work has been completed,
your licensed
plumber should inform the Water Authority as soon
as possible using Form WWO
46. Mains supply will be connected when the plumbing
work has been inspected and found satisfactory and after
you have paid the water
deposit and the charges for the connection work
and meter installation.
|