B188WC

Mainlaying within development at Anderson Road

Project Scope

Laying of about 4 800 metres (m) of fresh water mains of diameters ranging from 300 millimetres (mm) to 900 mm; and laying of about 4 800 m of salt water mains of diameters ranging from 150 mm to 400 mm.

Approved Project Estimate

$103.8M

Commencement Date

31/1/2008

Completion Date

25/8/2015

Current Progress

Completed

Project Office in WSD

Construction Division

Consultant

N/A

Contract

The proposed mainlaying works was incorporated into the site formation and associated infrastructure contract carried out by CEDD under 566CL.