9049WS

Salt Water Supply for Northwest New Territories – Stage 1

Project Scope

Laying of approximately 8.4 kilometres (km) of salt water mains of 1 000 millimetres (mm) in diameter along Castle Peak Road from Tsing Fat Street, Lok On Pai to Fu Tei, Tuen Mun; and construction of an intermediate booster chlorination plant at Tuen Mun water treatment works.

Approved Project Estimate

$188M

Commencement Date

25/2/2008

Completion Date

23/6/2014

Current Progress

Completed

Project Office in WSD

Construction Division

Consultant

N/A

Contract