Project Facts and Figures

Approved Project Estimate: $6,176M
Project Office in WSD: Consultants Management Division
Consultant: Black & Veatch Hong Kong Limited
Contracts: Contract No. 15/WSD/10 :
Expansion of Tai Po Water Treatment Works and Ancillary Raw Water and Fresh Water Transfer Facilities - Design and Build of New Stream II
Contractor: China State – ATAL Joint Venture
Commencement Date: February 2013
Completion Date: December 2019
Current Progress: completed
Contract No. 4/WSD/11 :
Construction of Butterfly Valley Fresh Water Primary Service Reservoir Extension and Associated Mainlaying
Contractor: Kwan On – China Geo Joint Venture
Commencement Date: September 2013
Completion Date: February 2018
Current Progress: completed